Design and build project for the MEP package for the extension of the Emergency Department at John Radcliffe Hospital, Oxford.
This project delivered extra treatment bays, diagnostic equipment, nurses’ bay and spaces for relatives.
The installation included the supply and commissioning of medical pendants, a new 500KVA HV Substation complete with back up remote generator, and IPS/UPS systems.
This project also included the construction of a new Ambulance Assessment Unit area for the hospital and the refurbishment of maternity theatres.
M&E Value | £3.6m | |
Region | Oxford | |
Client | Oxford University Hospitals NHS Foundation Trust | |
Main Contractor | McLaughlin and Harvey | |
Contract | NEC 3 Engineering and Construction Contract Option A | |
Design Responsibility | Irwin M&E | |
Duration | 18 months |