This project was for the full refurbishment of the plantroom within River House at Lagan Valley Hospital, Lisburn.
Works included the removal of all existing water damaged plant and equipment in the plantroom including ductwork, pipework and air handling unit (AHU).
We were also responsible for the installation of 2nr new AHUs, air conditioning system, ductwork, pipework and associated controls within the plantroom, as well as all associated electrical and builders’ works.
Electrical Value | £300k | |
Region | Lisburn, Co. Antrim, Northern Ireland | |
Client | South Eastern Health and Social Care Trust | |
Main Contractor | Irwin M&E Limited | |
Contract | GC/Works/1 Contract for Building and Civil Engineering Minor Works | |
Design Responsibility | Client Design | |
Duration | 5 months |